Floors Are Poured!

November 18, 2007 We are getting ready to head back to the states for a few rushed weeks of visiting with family, but were lucky to be here to see the floors poured.

This past Tuesday, we were on our way to Mercatale for our big weekly shopping and as usual decided to stop at the house. Just as we were heading up the road to the cemetery someone from the construction crew called to see if we were coming up! We got there just in time to see the cement being poured onto the top floor. One man was also building a small wall that will keep me from falling down to the bottom floor!



















The flooring is called "sotto......". It is very light--made from cement and a bunch of small styrofoam looking balls. This was only poured upstairs and covered all the tubes on the floor. Larry took this piece and laid it out to dry and when he went back the next day the only things left was the balls!
















Two days later a small crew came back and poured another layer upstairs and one downstairs. This was made of mostly sand with some cement and water. It seemed more like wet sand than cement. It was mixed by a small machine and then shot out of a tube upstairs that wiggled like a snake!
















They poured it, then leveled it, then buffed it! Both floors finished in one day by 3 men! They said it would take 2 days to dry enough to walk on and 2 weeks before the tile could be put down. Claver Battazzi (the foreman) told us it may take longer as it has been so cold (43 degrees as I write this at 2:00 in the afternoon).






















While we are in the states they will be cleaning up the "sassi" (rocks) walls and then putting plaster over the new walls and parts of the rock walls to cover the rocks that are "brutto" (ugly). Should be ready to lay the tile when we get back. Obviously, We won't be in before Christmas and probably not before the new year! Oh well. Siamo in Italia!

Friday, November 09, 2007

The continuing construction saga

Il 10 di novembre--The work goes on. There has been some progress but not much. Domenico, our favorite muratore has been creating his magic. Usually when we show up, he'll be there by himself doing work on the rock walls. We had a portion of our outside wall that enclosed a window and a small door that looked like a disaster. Three days, some cement, and the rocks taken out from where the arches now exist, Domenico working alone, transforms brutto (ugly) to bellissimo. Before and after.


















The plumbers are back. They are now laying the heating tubes to where the radiators will be. There will be about 16 radiators throughout our house. Many of them are required by law, even though we will have a large airtight fireplace, a wood burning stove in the kitchen and a small airtight wood burning stove in the bedroom.
































The "control room" under the pizza oven.







For some reason a wall was built along the wall downstairs. It covered up all the water outlets that were just installed. The plumbers show up and knock holes through the new wall to regain access? The plumbers weren't happy!